The Arizona Department of Transportation has announced its weekend work schedule that begins Friday, Sept. 23, and ends Monday morning, Sept. 26

  • Eastbound I-10 will be closed between US 60 and Loop 202 from 10 pm Friday to 4 am Monday for paving as part of the I-10 Broadway Curve improvement project.

The westbound US 60 ramp to eastbound I-10 will be closed as will the eastbound I-10 on-ramps at 40th Street and Broadway Road. The eastbound I-10 on-ramp at Chandler Boulevard will remain open. Eastbound US 60 off- and on-ramps at Mill Avenue will be closed. Both HOV lane ramps at the I-10/US 60 interchange will be closed.

Detour: The alternate freeway route to avoid the closure is eastbound Loop 202 to southbound Loop 101 and westbound Loop 202 in the Chandler area.

Drivers can also use I-10 in the West Valley to southbound Loop 202 to reach I-10 beyond the closure.

Eastbound I-10 drivers approaching the closure can detour on eastbound US 60, southbound Loop 101 and westbound Loop 202. Southbound SR 143 traffic entering eastbound I-10 will be detoured to eastbound US 60.

Notes: Northbound 40th Street will be closed between Broadway Road and I-10. Detour on northbound 48th Street/SR 143 to westbound University Drive.

  • Northbound Loop 303 will be closed between Van Buren Street (south of I-10) and Happy Valley Parkway from 10 pm Friday to 8 pm Saturday for pavement sealing. Both I-10 ramps to northbound Loop 303 will be closed.

Detour: Consider using northbound Loop 101 as an alternate freeway route.

Notes: Crews plan to reopen sections of northbound Loop 303 as they work north to south on the pavement sealing.

  • Southbound Loop 303 will be closed between Happy Valley Parkway and I-10 from 10 pm Saturday to 8 pm Sunday for pavement sealing. The southbound Loop 303 on-ramp at Jomax Parkway will also be closed.

Detour: Consider using local streets to southbound Loop 101 (alternate freeway route).

Notes: Crews plan to reopen sections of southbound Loop 303 as they work south to north on the pavement sealing.

  • I-17 will be narrowed to two lanes (left lanes closed) in both directions between Dunlap and Peoria avenues from 10 pm Friday to 5 am Monday for center barrier wall work related to Valley Metro’s light rail bridge construction project.
  • Westbound I-10 will be narrowed to one lane near Watson Road in Buckeye from 9 pm Friday to 4 pm Saturday and from 9 pm Saturday to 5 am Sunday for a freeway widening project.